(Super High Voltage Company of State Grid Ningxia Electric Power Co., Ltd, Yinchuan 750011, China)
Abstract: The existing cooling system of converter transformer is insufficient in heat dissipation potential during periods of heavy load,which to some extent leads to the deterioration of the operating conditions of the converter transformer, and has a negative impact on the life of the converter transformer. Under the premise that the existing converter transformer cooling method remains unchanged, this paper proposes a design scheme that uses the water spray method to help reduce the temperature rise of converter transformer body and cooler, the design process of each auxiliary cooling system and the calculation of the displacement of oil pool in rheological accident of the converter transformer are given, and good cooling effect is achieved in the work site. The scheme uses the cold water pool outside the valve of the existing converter station as the water source, has less input, is convenient for the operation and maintenance of the staff, and is convenient for the comprehensive management of the converter station, and has certain promotion value.
Key words: converter transformer; water spray; cooling system; dissipate heat
参考文献
[1] 雷战斐,宋海龙,刘舒杨.±800 kV 灵州换流站换流变压器风冷系统优化设计[J]. 宁夏电力,2017(3) :32-37.
[2] 刘杉,高冲,侯俊义,等. 基于去离子水冷却 ±800 kV 换流变压器阀侧套管的冷却效果和参数的影响[J]. 电工技术学报,2024,39(12) :3884-3894.
[3] 刘冀邱,张珊珊,熊凌飞,等. 高海拔特高压换流变压器冷却性能修正研究[J] . 高电压技术,2024,50(1) :242-249.
[4] 王之赫,冯轩,张中平,等. 换流变冷却器控制逻辑研究及典型案例分析[J]. 电工技术,2022(24) :179-180.
[5] 于鹏,殷丕盛,赵航,等. 默拉直流换流变冷却系统研究及常见故障分析[J] . 电子制作,2022,30(24) :93-95.
[6] 杨柳,张丽,周月宾,等. 柔性直流换流阀与水冷变压器外冷却系统一体化设计方案[J] . 南方电网技术,2021,15(6) :15-19.
[7] 李星辰,廖毅. 天广直流换流变冷却系统电源自动切换回路研究[J]. 通信电源技术,2018,35(9) :139-140.
[8] 王伟,罗宗源,张瑞亮. 高肇直流换流变冷却系统电源切换回路分析与改进[J]. 电工技术,2018(2) :34-35.
[9] 李毅,崔学龙,陈亮. 贵广Ⅰ 回直流系统换流变压器冷却器的节能研究[J] . 南方电网技术,2013,7(5) :43-45.
[10] 刘浔,艾亮,成川,等. 换流变冷却器全停对高压直流系统影响[J]. 山东工业技术,2018(17) :166.
[11] 肖磊磊,林永宏,查光年. 换流变压器冷却系统电源自动切换回路分析[J] . 南方电网技术,2012,6(2) :47-50.
[12] 王晨睿. 宜宾换流站换流变压器冷却器应对交流电网扰动隐患分析[J]. 四川电力技术,2018,41(4) :85-89.